Monday, August 27, 2012

Day 83
July 13th, 2012

This post will cover on 2 topics - 1) Plinth beam casting and 2) Retrospective of Foundation

Plinth Beam Casting
Plinth beam is the horizontal cement beam across the house perphery laid on top of foundation.
This picture shows how the finished plinth beam looks.            

Purpose of the plinth beam is to:
  1. Prevent leaking of water into foundation - To prevent a house from settling it is critical that no water be leaked into foundation. Being made of cement, plinth beam is impervious and therefore prevents water from rain, flooding, etc. from leaking into foundation. 
  2. Provides support for walls - For load bearing houses, walls carry the weight of the house. Plinth beam provides solid footing to raise those walls.
  3. Holds house together - Since plinth beam sits across the periphery of the house, it provides binding force across rooms. For example, without plinth beam it is possible for one of the rooms to settle thus creating uneven floor level. Plinth beam prevents that from happening. 


Basic process to construct plinth beam is as follows: 

  1. Mark-up width - Usually width of plinth is half that of the foundation. In this case, foundation is about 18" wide and so plinth is 9" aligning with the outer edge of the foundation. Inner 9" of foundation meshes into the floor level of the house. 
  2. Lay down the steel beam - As the adjacent picture shows beams are the core of the plinth beam.  Beams have a loop every 6" that holds it together. 
  3. Setup re-inforcement - Before concrete is poured, re-inforcement has to be established to provide rectangular shape to the beam. This takes majority of effort as planks have to be nailed properly in place and once concrete is poured they need to be removed. 
  4. Pour the concrete - Next step is to pour the concrete. As concrete is poured, mason ensures that it is evenly spread and smoothens out any edges. He also needs to ensure the height of the beam is consistent throughout the periphery. 
  5. Remove re-inforcement - Concrete turns solid within 24-hour and final step is to remove the planks leaving the beam intact. 



This short video explains this process in action. 


Foundation Redone:

To give background context, ground level at living room area is 1' higher than that at the guest bedroom level. Typical height of plinth level is 2.5' that includes 1' of plinth beam and 1.5' of foundation masonry. Turns out though that foundation masonry was 2.5' at living room and 3.5' at guest bedroom. What this meant was plinth height would be 3.5' from natural ground level. This was realized only when plinth beam casting was about to start. To add to misery, by then Rainwater tank was already done to align with 3.5' of plinth !

My architect was clear that plinth level can be no taller than 2.5' or else house would look place oddly high. What followed was no fun - We ended-up undoing a few days of work. Specifically

  • Reduce Rainwater tank height by 1' by chipping away at just-finished concrete tank
  • Remove 1-layer of foundation stone masonry from across the house periphery to reduce the foundation height by 1'. 


Here is the clip of work being undone. It could have been worse had plinth beam been built. Good news was we caught it at a time that cost us about a week and some cost in material and labor. Having said that, there were key lessons learnt -


  1. Trust your gut instinct - Even though as homeowners we may not be in construction business, you have a feel for what's going on. I certainly did feel that foundation was looking tall. While "plinth" was a new term and I didn't know that it was 1' in height I concluded I knew no better. That was the critical mistake. No question is a dumb question especially when you are new to the domain. Had I had surfaced my instinct more strongly or did some research things could have been different. 
  2. Working drawing consultation - I independently found my architect and contractor. So they had no prior relationship between them. When architect released drawings there was no consultation that occurred between the two. So, architect didn't get a chance to explain the nitty-gritty and contractor felt drawings were clear-enough. A big no-no ! It is critical that drawings are released to contractor only after architect has had a chance to explain them to the contractor. It is best to have such meetings at the site to relate paper drawings to the actual mapping onsite. Often times, what looks right on paper doesn't feel right to the eye. If that's not possible, have them meet at architect's office. 
  3. Inspection schedule - Identify stages at which architect would come and inspect the site to validate it is built according to the specifications. In this case, architect mentioned a couple of times need to schedule inspection. However, given that this was first or second inspection we were not as diligent as needed. 

Again, in retrospect, it was not a terrible setback.. Like many other things in life, none of the lessons were new; rather they were re-inforcement of what you would learn at many other times. Lessons learnt were critical and have since been put in practice. There is now tighter collaboration between me or my wife, architect and the contractor and crisper conversation about respective point of view. So, in the end it definitely had a silver lining !

27 comments:

  1. Thanks for this information. I have always been interested in builder’s. Great article.
    Chinchilla Builders | Dalby Builders | Toowoomba Builders

    ReplyDelete
  2. Hi there! great post. Thanks for sharing a very interesting and informative content, it is a big help to me and to others as well, keep it up!

    Kit Homes NSW | Kit Homes Australia

    ReplyDelete
  3. really super sir. that will be really helpful

    ReplyDelete
  4. really super very interesting very very thanks

    ReplyDelete
  5. informative ...!!!!! thanks a ton

    ReplyDelete
  6. i like this info & more useful to us. can u give any customer link to me for construction.just it is my request ,don't make me mistake (rameshmagesh@gmail.com) thank u.

    ReplyDelete
  7. This comment has been removed by the author.

    ReplyDelete
  8. Thanks for your efforts Kaushal. It's indeed a great post. Would you please be kind to share few pictures of your house. We are starting the construction of our house very soon.

    ReplyDelete
  9. Great Information. Thanks for share nice blog. Ultratech cement are the manufacturers of building construction materials from India.

    ReplyDelete
  10. This comment has been removed by the author.

    ReplyDelete
  11. Hi, than you very much for the answer. If the plinth is around 1.5m above NGL, is it necessary to provide 2 beams? Is one beam at the NGL good enough?

    Also can there be any other implication of not providing a plinth beam besides uneven floor level? It can also be avoided by reinforcing the floor at plinth level right?

    ReplyDelete
  12. hello sir

    I am constructing my own house in Hyderabad, after completion of footing,columns raised to certain level,and filled plot with soil up to plinth beam bottom level. after that we directly done the marking of plinth beams between the columns on 1'' layer of cement on soil with out CRS walls for plinth beams.

    my question is does CRS walls required as a foundation between the columns before plinth beam marking or not?

    ReplyDelete
  13. Hello Sir, I am extending my first floor to one more level. The existing Ground level built with 9" X 9" column. This will be extended for another 10' feet for my first floor. The contractor has a shutter height of 5'. If the first 5' inch is raised, how many days I need to wait to continue the remaining 5' feet. Please advise me.

    ReplyDelete
  14. Your blog article ie really very nice and beneficial which makes it informative blog article. Thanks for sharing it and keep sharing.
    Building Materials

    ReplyDelete
  15. Really very great blog!!!Building and construction industry is one of the fastest growing sectors not only in India but also throughout the globe.
    Indian construction magazine

    ReplyDelete
  16. Great Information. Thanks for share nice blog. Ultratech cement are the manufacturers of Aluminium Scaffolding Manufacturer in chennai.

    ReplyDelete
  17. I discovered this type of large amount of fascinating stuff in your online journal particularly its discourse. From the huge amounts of remarks in your articles, I figure I'm not by any means the only person having most of the pleasure here! keep doing awesome….water in crawl space

    ReplyDelete
  18. Westerners worry about excessive development in China, and some of the country's untouched and unspoiled landscapes have been targeted by the central government, including the only remaining "virgin river", the Nu in Yunnan Province. Whether the authorities can strike a balance between economic growth and environmental protection is one of the key issues facing the country. Builders Gold Coast

    ReplyDelete
  19. DABBL is a top manufacturer and distributor company of the large range of Bathroom Shower Enclosures, Shower Cubicle, Custom, Sliding, Frameless Glass Shower Doors, Shower Stall, Shower Screen and Many More. We offer a best quality and design product that fits to any expectation of the Consumer Contact us sale2@dabbl.com more details visit here Shower Cubicle, Shower Enclosures, Glass Shower Doors, Screen, Trays

    ReplyDelete
  20. Hi Admin, Really Good Post! Keep sharing your post on House Design & House Plans, Architecture 3D Elevations. I like your content and will recommend others to read out your blog House Design

    ReplyDelete
  21. Good Work!!
    Great Article!! Very informative.
    Also check out For properties in Bangalore.
    The silicon city of India.
    Land India

    The Green City of India.
    Land India

    Land in Bangalore.
    Land India

    BUY-SELL-RENT
    Land India


    ReplyDelete
  22. I'm not sure exactly why but this site is loading very slow for me. Is anyone else having this issue or is it a issue on my end? I'll check back later and see if the problem still exists. Alex Shcolyar

    ReplyDelete